THE APPLICATION OF SECONDARY CRUSHING AT THE JUNDEE GOLD MINE

You are here: Resources / THE APPLICATION OF SECONDARY CRUSHING AT THE JUNDEE GOLD MINE

K MATSON, S TYRRELL AND B JACKSON

14thAusIMM Mill Operators’ Conference, 29-31 August 2018, Brisbane, Australia

Australia

ABSTRACT

Northern Star Resources Limited Jundee Gold Mine in Western Australia operates a comminution circuit that

consists of a primary crusher, 3.85 MW semi-autogenous grinding (SAG) mill, 1.8 MW ball mill and pebble

recycle crusher. In 2017, a secondary crushing circuit was installed to remove the SAG mill throughput

bottleneck and increase production of highly competent underground ore from 1.35 to a minimum of 1.7

Mt/a.

This paper discusses the findings from the trial phase, the circuit design, project delivery, site optimisation,

and the plant performance.

AUTHOR DETAILS

K MATSON (1), S TYRRELL (2) AND B JACKSON (3)

(1) MAusIMM, Senior Metallurgist, Northern Star Resources Limited, Perth WA 6008. Email: This email address is being protected from spambots. You need JavaScript enabled to view it. 

(2) MAusIMM(CPMet), Chief Metallurgist, Northern Star Resources Limited, Perth WA 6008. Email: This email address is being protected from spambots. You need JavaScript enabled to view it.

(3) MAusIMM, Metallurgical Superintendent, Northern Star Resources Limited, Perth WA 6008. Email: This email address is being protected from spambots. You need JavaScript enabled to view it.

ACKNOWLEDGEMENTS

CEEC acknowledges and thanks The Australian Institute of Mining and Metallurgy for organising the 14thAusIMM Mill Operators’ Conference (MillOps 2018). 

Abstracts can be found at the MillOps website.

Categories

0