K MATSON, S TYRRELL AND B JACKSON
14thAusIMM Mill Operators’ Conference, 29-31 August 2018, Brisbane, Australia
Australia
ABSTRACT
Northern Star Resources Limited Jundee Gold Mine in Western Australia operates a comminution circuit that
consists of a primary crusher, 3.85 MW semi-autogenous grinding (SAG) mill, 1.8 MW ball mill and pebble
recycle crusher. In 2017, a secondary crushing circuit was installed to remove the SAG mill throughput
bottleneck and increase production of highly competent underground ore from 1.35 to a minimum of 1.7
Mt/a.
This paper discusses the findings from the trial phase, the circuit design, project delivery, site optimisation,
and the plant performance.
AUTHOR DETAILS
K MATSON (1), S TYRRELL (2) AND B JACKSON (3)
(1) MAusIMM, Senior Metallurgist, Northern Star Resources Limited, Perth WA 6008. Email:
(2) MAusIMM(CPMet), Chief Metallurgist, Northern Star Resources Limited, Perth WA 6008. Email:
(3) MAusIMM, Metallurgical Superintendent, Northern Star Resources Limited, Perth WA 6008. Email:
ACKNOWLEDGEMENTS
CEEC acknowledges and thanks The Australian Institute of Mining and Metallurgy for organising the 14thAusIMM Mill Operators’ Conference (MillOps 2018).
Abstracts can be found at the MillOps website.